Commercial solar installation in Nova Scotia lets a plant, warehouse or farm generate its own electricity and buy less from Nova Scotia Power. At Goodspeeds Manufacturing in Lakeside, our 90.48 kW DC system offsets 97.53% of annual electricity use. NS Power’s Commercial Net Metering Program credits your generation kWh for kWh against the electricity you buy, up to 1,000 kW AC for a business on a demand rate. Green Integrations installs rooftop solar and battery storage for commercial and industrial buildings across the province.

The work begins with your NS Power bills, and you see the projected payback before you choose a system.

Commercial rooftop solar installation by Green Integrations
Goodspeeds ManufacturingLakeside90.48 kW DC
C&I projects delivered since 2012
360+
Payback on completed projects
4.6–7.6 yr
Project IRR on completed projects
15–30%
Incentive funding secured
$20M+

Cost

Commercial solar cost in Nova Scotia

$1.30–$2.10per watt DC installed, before incentives and HST

Commercial rooftop solar in Nova Scotia costs about $1.30 to $2.10 per watt DC installed, before incentives and HST (Harmonized Sales Tax). The larger the system, the lower in that range it usually lands.

If NS Power has to add or upgrade equipment to connect your system, you pay for that work, and the final amount is reconciled against what it actually cost. What moves the price per watt is covered in our guide to what commercial solar panels cost in Canada.

Installed cost before incentives and yearly generation · Nova Scotia rooftop
System size (DC)Installed cost before incentivesYearly generation
100 kW$130,000 to $210,000105,000 to 109,000 kWh
200 kW$260,000 to $420,000210,000 to 218,000 kWh
500 kW$650,000 to $1,050,000525,000 to 545,000 kWh
1 MW$1,300,000 to $2,100,0001,050,000 to 1,090,000 kWh
  1. Market range$1.30 to $2.10 per watt DC, before incentives and HST
  2. System sizeThe larger the system, the lower in the range it usually lands
  3. Connection workYou pay for any NS Power equipment added or upgraded, reconciled against actual cost

Net metering

NS Power Commercial Net Metering and the 1,000 kW limit

Systems up to 27 kW AC connect through NS Power’s Self-Generating Option. Above that, a business joins the Commercial Net Metering Program, where your rate or your type of operation sets the limit. Limits are in kW AC, the inverter rating, while array size and price are in kW DC. Within the limit the system can meet your expected annual use but cannot exceed it.

Commercial Net Metering limits by customer
CustomerLimit
Rate with a demand charge1,000 kW AC
Registered farm, registered winery or licensed aquaculture plant1,000 kW AC
Any other commercial customer200 kW AC

One system can serve several accounts in the same distribution zone if they are registered to the same legal entity and share a non-residential rate code, and you propose how the surplus is split between them. A battery does not count toward your limit, although NS Power includes it when it sets your interconnection class and studies the connection.

Self-Generating Option · up to 27 kW ACLimits in kW AC · price in kW DC

How net metering credits work

Your generation offsets the electricity you use, and anything above that in a billing period is banked in kWh for later bills. Banked credits run until January 1. Whatever is left then is applied to electricity you were billed for in the same calendar year, as a bill credit on your first bill of the new year. Credits beyond that amount are forfeited, and banked credits have no cash value. That is why we size to your annual use, not to your roof.

Incentives

Commercial solar incentives in Nova Scotia

Among the rebates and incentives open to a Nova Scotia business, the federal tax credits are the largest. Efficiency Nova Scotia’s SolarHomes rebate now serves registered non-profits and charities only, after closing to homeowners on April 17, 2025.

Program information reviewed: November 2026
Federal

Clean Technology Investment Tax Credit, or ITC

Refundable tax credit
30%of capital costs

Refundable credit of up to 30% of capital costs, net of other incentives.

Main conditions

Taxable Canadian corporations; the full rate depends on the prevailing wage and apprenticeship conditions.

10%of the capital cost

10% of the capital cost of new qualified property.

Main conditions

Sector test, including manufacturing and processing, farming, fishing and logging; refundable only for qualifying corporations, otherwise carried back 3 years or forward 20.

Federal

Enhanced First Year Capital Cost Allowance

Tax deduction
100%first-year write-off

100% write-off in the first year.

Main conditions

Applies to the net cost after rebates and tax credits.

Stacking

The two federal credits work together. In a 2024 technical interpretation the Canada Revenue Agency worked through solar panels powering a Halifax manufacturer, and neither credit reduced the other. The Atlantic credit depends on how the property is used, so we check your sector before it goes into your model. Efficiency Nova Scotia’s Business Energy Rebates offer up to 50% of product costs on energy efficient products, which can help fund efficiency measures evaluated alongside the array.

Payback

Commercial solar payback in Nova Scotia

Your payback and ROI come from your NS Power rate, because net metering credits count against the electricity you buy, while base and demand charges stay on the bill. The demand charge is set by your highest power draw. These are the business rates in effect from May 1, 2026.

NS Power business rates from May 1, 2026
NS Power rateWho it fitsEnergy chargeDemand charge
Small General (Rate 10)Under 45,000 kWh a year19.804 cents for the first 200 kWh a month, then 17.997 centsNone
General Demand (Rate 11)Over 32,000 kWh a year, demand under 1,800 kW15.738 cents for the first 200 kWh per kW of demand, then 12.674 cents$9.809 per kW
Small Industrial (Rate 21)Industrial use including farming and processing, demand under 225 kW14.531 cents for the first 200 kWh per kVA of demand, then 12.215 cents$7.496 per kVA
Medium Industrial (Rate 22)Industrial use, demand from 225 kW to under 1,800 kW11.367 cents$10.71 per kVA
Large General (Rate 12)Non-industrial use, demand of 1,800 kW and over11.78 cents$11.174 per kVA
Large Industrial (Rate 23)Industrial use, demand of 1,800 kW and over11.205 cents$9.268 per kVA

On a stepped rate, the first kilowatt-hours you buy each month cost more and the rest cost less. Solar removes the cheaper ones first and reaches the higher step only if your net purchases fall that far. Your average cost per kWh is higher because it includes the demand charge: NS Power’s sample for the General Demand rate is 22.55 cents per kWh at a 20% load factor, meaning a site with sharp peaks, while solar replaces electricity priced at 12.674 to 15.738 cents. We model savings on the energy charge you actually avoid. The wider picture is in our guide to how much a business can save.

Worked example · federal tax credits

Example: a 100 kW system at a manufacturer

A 100 kW DC system at $1.80 per watt on a Small Industrial account, at the full federal credit rate:

100 kW DC$1.80 / WRate 21
Installed cost
$180,000
Clean Technology ITC, 30%
−$54,000
Atlantic Investment Tax Credit, 10%
−$18,000
Cost after tax credits
$108,000

Estimated savings in a year

$12,826

105,000 kWh at 12.215 cents.

Estimated simple payback

About 8.4 years

Then

The first-year write-off on the net cost shortens that payback, and so would any rate increase.

Halifax · Dartmouth · HRM

Commercial solar in Halifax and Dartmouth

Commercial and industrial solar panel installation in Halifax, Dartmouth and the rest of the Halifax Regional Municipality follows the NS Power rules above, plus a municipal solar collector permit. The application needs an engineered design showing how the panels connect to the roof, and the final inspection needs proof of a completed NS Power site inspection and electrical permit. Structural changes to a commercial roof call for a Commercial Building Permit.

Truro to Cape Breton

Commercial solar outside Halifax

From Truro to Cape Breton, a rural project starts with the electrical service at the site. A system above 27 kW AC on a single-phase circuit needs a Preliminary Assessment, and its results can add technical requirements or restrict capacity, so we check the service before sizing the array. Antigonish, Berwick, Lunenburg, Mahone Bay and Riverport have their own municipal electric utilities. Commercial Net Metering is an NS Power program, so in those towns we confirm the local utility’s terms first.

Storage

Solar and battery storage for Nova Scotia facilities

Battery storage can reduce the demand charge where your load profile and rate support it, and the Clean Technology ITC covers storage as well as solar.

Winter peaks

On Large General and Large Industrial accounts, the billed demand can be the highest reading from the previous December, January or February, so a winter peak can set the charge for months.

Outages

Staying on through an outage takes special transfer and isolating equipment, because a grid-connected system otherwise has to disconnect until NS Power has restored service.

Industries

Commercial solar for Nova Scotia industries

Manufacturing

Production equipment, lighting and building systems give a plant a stable electricity profile, which is what the Goodspeeds array was sized against.

97.53%Goodspeeds, Lakeside · offset

Warehousing

Large flat roofs suit commercial solar, and ballasted or mechanically attached racking works with most flat membrane roofs without penetrations.

Agriculture, wineries and aquaculture

A registered farm, registered winery or licensed aquaculture plant without a demand charge still qualifies for the full 1,000 kW AC.

1,000 kWAC net metering limit

Commercial real estate

Credits land on the account that holds the system, so we settle whether that is the owner or the tenant before design.

Non-profits and charities

Community halls, legions, religious institutions and other groups on NS Power’s Charitable rate pay 19.128 cents per kWh, so a kWh of solar saves more than on any demand rate in the table. In Halifax, Solar City, the municipality’s financing program, offers non-profits, places of worship, co-operatives and charities 10-year financing at a fixed 4.75%.

19.128¢per kWh on the Charitable rate

Process

Our commercial solar installation process in Nova Scotia

Four stages, with the NS Power application built in.

  1. Bills and financial model

    We read your bills and interval data (your meter’s readings through the day) to find the rate class, the system size and the savings, at no cost to you. You get an annual production model and a capital plan with incentives and financing built in. An energy audit can add efficiency measures to that plan, so the array is sized to the load you expect to have.

    Outcome
    • Annual production model
    • Capital plan
    • No cost
  2. NS Power application

    We complete the structural, electrical, permitting and utility deliverables, and the system size sets the path. Class 1 covers more than 27 kW up to 100 kW AC. It starts with an Interconnection Request and a $57 plus HST fee, and NS Power reviews your eligibility, equipment and system size. A single-phase site also pays $750 for its Preliminary Assessment. Class 2 covers more than 100 kW up to 1,000 kW AC and follows the Distribution Generator Interconnection Procedures: a $750 non-refundable study fee, a Preliminary Assessment within 30 calendar days, then a Distribution System Impact Study with a $10,000 deposit.

    Interconnection class
    • Class 1 · over 27 to 100 kW AC
    • Class 2 · over 100 to 1,000 kW AC
  3. Permits, construction and connection

    The electrical contractor on your project obtains a wiring permit and submits electrical plans to NS Power before installation begins, and the work is planned around your production. Once inspections pass and your agreements with NS Power are signed, NS Power clears the connection and may witness commissioning. If your meter cannot measure in both directions, NS Power replaces it at no cost.

    Nova Scotia context
    • Wiring permit
    • NS Power clears connection
  4. Verification and operation

    Reports at 6 and 12 months compare output with your model, solar maintenance keeps the system producing, and your engineer stays with the project through year 25.

    Outcome
    • Reports at 6 and 12 months
    • Same engineer to year 25

FAQs

Nova Scotia commercial solar FAQs

Not covered here? A 20-minute call with an engineer usually answers it.

Yes, as long as a facility has steady electricity use through the year. More Nova Scotia businesses are making that call. NS Power counted 99 new commercial solar installations in 2025, up 41% from 2024.

Send us your NS Power bills

We will come back with the system size, the net metering class and a projected payback for your facility, at no cost.